The next scheduled Turf application will be completed in October. This application is a dormant feeding that will prepare turf for the winter months.
Have a great Labor Day weekend!
Completed Items This Week
Turf fertilization and weed control was completed in Neighborhoods 7, 8 and 9.
Stick edging of sidewalks was completed in Neighborhoods 9,8,7,4, and 3.
Edging & Cultivation was completed in Neighborhood 7.
Scheduled Landscape Items Next Week
Edging of sidewalks will be completed in residential neighborhoods 2 and 5.
Monthly walking trail mowing will be completed.
Complete Edging & Cultivation in Neighborhood 8.
Begin Edging & Cultivation in Neighborhood #9.
Mowing Schedule for 2011
The General Mowing Schedule will be: Neighborhood 1 & 10 will be serviced Monday’s. Neighborhood 9&8 will be serviced Tuesday’s. Neighborhood 7&5 will be serviced Wednesday’s. Neighborhood 4&3 will be serviced Thursday’s. Neighborhood 2 will be serviced on Friday’s. Grand Dominion Common Areas will be mowed on Wednesday’s for the remainder of the season. Please understand that weather may alter this schedule.